2,061 GWactive interconnection queue at year-end 2025, about one and a half times the operating fleet. 549 GW of it holds a draft or executed interconnection agreement, though more than 40 percent of capacity withdraws even after that stage.LBNL, Queued Up: 2026 Edition
13%of queued capacity has historically reached operation, while three quarters is withdrawn. Median duration now exceeds five years.LBNL, Queued Up: 2026 Edition
8+ yearsPJM's average interconnection application to commercial operation in 2025, from under two years in 2008.RMI, 2026
4 auctionsconsecutive PJM capacity auctions that hit administrative price caps, most recently $325/MW-day. The December 2025 auction fell 6,623 MW short of its reliability requirement.PJM auction reports
$2.2B to $16.4BPJM annual capacity cost across four years of auctions, spread across 67 million people in 13 states and DC.PJM
84% and 93%declines in utility-scale solar levelized cost since 2009 and in battery pack prices since 2010. Solar is $40-98/MWh unsubsidized against $144-276 for a gas peaker.Lazard LCOE+ 2026; BloombergNEF 2025
+33%nominal residential electricity rates since 2019. Electric and gas utilities requested a record $31 billion of rate increases in 2025, double the prior year, and only two of the 83 cases tracked were rejected.LBNL, 2026; PowerLines, 2026
~5 yearslead time for heavy-duty gas turbines, up from about two years in 2019. GE Vernova's gas backlog plus slot reservations grew from 83 GW to 100 GW in a single quarter.IEEFA; GE Vernova 8-K, April 2026
~100 GWof new large load that could be integrated on the existing grid with modest curtailment flexibility, avoiding roughly $100 to $220 billion of generation capital.Nicholas Institute, Duke University, 2025
~2x capacityfrom reconductoring existing corridors with advanced conductors, at roughly half the cost of new build and with limited new permitting. DOE lent AEP Texas up to $3.26 billion to do it across 2,800+ miles.Chojkiewicz et al., PNAS 2024; DOE, July 2026